UPCOMING NIGHT WORKS: SEWER MAIN WORKS – SOUTH ROAD AND TORRENS ROAD INTERSECTION – 22/09/2016 – 26/09/2016

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be installing a new sewer main on the eastern side of South Road at the Torrens Road intersection.

To minimise disturbance to peak hour traffic, the works will take place between:

  • 7pmThursday 22 September and 1am Friday 23 September; and
  • 7pm Friday 23 September to 6am Monday 26 September 2016.

Key activities

  • Identification of services.
  • Saw cutting of the pavement.
  • Excavation of a trench and pipe laying.
  • Backfill, reinstatement and asphalting.

Traffic Management

  • Traffic and speed restrictions at the Torrens Road Intersection with South Road and on South Road between Tait Street and Dartmouth Street (for southbound traffic) will apply while works are in progress.
  • Signage will alert motorists to the changed traffic conditions.

Some noise disturbance can be expected at times while these works are completed, however the work will be managed to minimise disturbance to local residents as much as possible.

For further information about these works please contact us on: 1300 794 899, or email at: enquiries@t2talliance.com.au