CONTINUATION OF NIGHT WORKS: INSTALLATION OF A WATER MAIN ON SOUTH ROAD AT THE HYTHE STREET INTERSECTION – 29/11/2016 – 1/12/2016

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be continuing the installation of a new water main on the eastern side of South Road. Crews are currently working across various sites between McInnes Street and Torrens Road.

Hythe Street will be temporarily closed at South Road each night between 7pm and 6am, from Tuesday 29 November to Thursday 1 December 2016 to facilitate these works.

Key activities

  • Identification of services, saw cutting of the road pavement.
  • Excavation of a trench, pipe laying and reinstatement.

A vacuum truck, road saw, mobile crane, excavator, compaction equipment, trucks and light vehicles will be used to perform these works. Lighting towers will also be in operation during night works.

Traffic Management

  • No traffic will be able to enter or exit Hythe Street at South Road during this period.
  • Local detour routes will be in place during temporary road closures.
  • Traffic and speed restrictions will apply in the vicinity of the works.
  • Signage will alert motorists to the changed traffic conditions.
  • Pedestrian access on South Road will be maintained with the assistance of a traffic controller.

Works will be managed to minimise disturbance to local residents however some noise can be expected.

For further information about these works, including the latest traffic arrangements, please contact us on: 1300 794 899, or email: enquiries@t2talliance.com.au