UPDATE: UPCOMING NIGHT AND WEEKEND WORKS AT THE SOUTH ROAD INTERSECTION WITH TORRENS ROAD – 09/06/2017 – 12/06/2017

As per the works notice dated 26 May 2017, the stormwater works in the u-turn facility at Tait Street were completed, however, stormwater works were not undertaken in another location of the South Road intersection with Torrens Road as planned.  Refer below, to the remaining works to be completed.

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be installing new stormwater infrastructure on South Road, on the south west corner of the intersection with Torrens Road from 7pm Friday 9 June to 6am Monday 12 June 2017.

Key activities                                                                                               

  • Saw cutting of the road pavement and installation of stormwater pits and pipes.
  • Reinstatement of pavement.

A vacuum truck, road saw, mobile crane, excavator, compaction equipment, asphalt paver, trucks and light vehicles will be used to perform these works. Lighting towers will also be in operation during night works.

Traffic management

  • Access to driveways will be maintained during these works.
  • Pedestrian access will continue to be provided at the intersection.
  • Lane and speed restrictions will apply in the vicinity of the works.
  • Signage will alert motorists to the changed traffic conditions.

Works will be managed to minimise disturbance to local residents however some noise can be expected.

For further information about these works please contact us on: 1300 794 899, or email at: enquiries@t2talliance.com.au