UPDATE: UPCOMING NIGHT AND WEEKEND WORKS AT THE SOUTH ROAD INTERSECTION WITH HAWKER STREET – 15-18 SEPTEMBER 2017

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be undertaking stormwater and signalling works at the South Road intersection with Hawker Street.

These works did not proceed as previously advised and will now take place from 7pm Friday 15 September to 6am Monday 18 September 2017.  

Key activities

  • Installation of stormwater infrastructure.
  • Installation of traffic signalling conduits.

An excavator, road saw, vacuum truck, backhoe, bob cat, trucks, compaction equipment and light vehicles will be used to perform these works. Lighting towers will also be in operation during night works.

Traffic management

  • Lane and speed restrictions will apply on South Road in the vicinity of the works.
  • Signage will alert motorists to the changed traffic conditions.
  • Pedestrian access will continue to be provided under the guidance of traffic control.

Some noise can be expected, however the work will be managed to minimise disturbance to local residents as much as possible.

For further information about these works please contact us on: 1300 794 899, or email at: enquiries@t2talliance.com.au