UPDATE: UPCOMING NIGHT AND WEEKEND WORKS FOR WORKS ON TORRENS ROAD, CROYDON PARK

Further to our notice dated 12 July 2016, some of the stormwater works on Torrens Road referred to in that notice have been re-scheduled. Below is a list of weekend works that will now occur on Torrens Road between
Friday 15 July and Sunday 24 July 2016.

  • Preparation works for installation of the storm water pipe near the South Road intersection:

Friday 15 July 2016 7pm to 11.30pm

  • Telstra service relocation works opposite Ellen Street:

Saturday 16 July and Sunday 17 July 2016 from 7am to 5pm each day

  • Re-scheduled stormwater works near South Road intersection:

7pm Friday 22 July to 7pm Sunday 24 July 2016

  • Continuation of Telstra service relocation works opposite Ellen Street:

Saturday 23 July and Sunday 24 July 2016 from 7am to 5pm each day

Activities

Works will involve pavement cutting, excavation of the road, service installations, backfill and reinstatement works.

An excavator, vacuum truck, mobile cranes, road saw, compaction equipment and light vehicles will be in operation during these works. Lighting towers will also be used during night works.

Traffic Management

  • Traffic and lane restrictions will be in place on Torrens Road.
  • Traffic and speed restrictions will apply in the vicinity of the works.
  • Signage will alert motorists to the changed traffic conditions.
  • Driveway access will be maintained.

For further information about these works, including the latest traffic arrangements, please visit contact us on: 1300 794 899, or email: enquiries@t2talliance.com.au.