As part of the Torrens Road to River Torrens Project, the T2T Alliance will be continuing works on the lowered motorway in South Road, between Forster Street and Torrens Road.
Works will continue intermittently between 7pm and 6am from Monday 30 October to Thursday 30 November 2017.
Key activities
Excavators, loaders, vacuum truck, hand tools, trucks and light vehicles will be used to perform these works. Lighting towers will also be in operation during night works.
Traffic Management
No additional pedestrian or traffic management will be required to carry out the lowered motorway excavation works.
Lane and speed restrictions will apply on South Road in the vicinity of the sign installation works.
Works will be managed to minimise disturbance to local residents however some minor noise can be expected at times.
For further information about these works please contact us on: 1300 794 899, or email at: enquiries@t2talliance.com.au