UPDATE: UPCOMING DAY WORKS ON LAMONT STREET

Due to recent poor weather conditions, works to install a new sewer main in Lamont Street, between South Road and Days Road, have been delayed.

The works which have commenced at the South Road end of Lamont Street will take approximately two months to complete.

To minimise disturbance to residents the works are being undertaken from Monday to Friday between the hours of 7am and 6pm.  Some weekend works may be required, however, you will be notified separately if this occurs.

Key activities

  • Service depthing to identify location of services
  • Excavation of a trench in the middle of the roadway
  • Installation of a sewer main
  • Backfill and reinstatement of the trench

An excavator, trucks, mobile cranes, compaction and asphalting equipment and light vehicles will be used to perform these works.

Some noise can be expected while these works are completed, however the work will be managed to minimise disturbance to local residents as much as possible.

Traffic management

  • Lamont Street will be CLOSED to traffic in the vicinity of the works.
  • Signage will alert motorists to the changed traffic conditions.

For further information about these works, including the latest traffic arrangements, please visit: www.t2talliance.com.au

Driveway access restrictions

Works will progressively move down the street. When works are directly in front of properties, temporary restrictions to property driveways for approximately three days will be required. A member of the T2T Alliance will visit affected properties in advance of driveway restrictions being implemented, to discuss the timing of these works and alternative parking arrangements if required.

Please contact us on: 1300 794 899, or email: enquiries@t2talliance.com.au if you would like to speak to a member of the project team about these works and to discuss your individual needs.