UPDATE: TEMPORARY ROAD CLOSURE – BISHOP STREET AND SOUTH ROAD, RIDLEYTON – UNTIL EARLY NOVEMBER 2017

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be continuing a range of activities in the southbound lanes of South Road between Pym Street and Torrens Road.

To safely undertake these works the Bishop Street junction with South Road will continue to be temporarily closed until early November 2017.

Key activities

  • Undergrounding of electrical services
  • Installation of new water main
  • Installation of common services trench
  • Installation of new kerbing and footpath

The works will be undertaken daily between 7am and 6pm from Mondays to Saturdays, unless otherwise advised.

Traffic management

  • The Bishop Street junction with South Road will continue to be temporarily closed until 6am Monday 30 October 2017. During this time access to Bishop Street will be via Ferris Street, Wright Street or Harrison Road.
  • Tait Street and Sunbeam Road will continue to remain open during this time.
  • Signage will alert motorists to the changed traffic conditions.

For further information about these works please contact us on: 1300 794 899, or email at: enquiries@t2talliance.com.au