Due to scheduling conflicts these works will not proceed in March 2017 as previously advised below.

Residents and businesses will be notified of the new dates once the works are rescheduled.

_________________________________________________________________

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be undertaking pavement works in preparation for the opening of the new northbound surface road on South Road between Tait Street and Pym Street.

To minimise disturbance to peak hour traffic, the works will take place over two weekends, from:

  • 7pm Friday 17 March to 6am Monday 20 March 2017
  • 7pm Friday 24 March to 6am Monday 27 March 2017

Key activities

  • Installation of kerbing.
  • Asphalting and line marking.