UPCOMING WORKS ON SOUTH ROAD BETWEEN DAY TERRACE AND TORRENS ROAD – 3-16 OCTOBER 2017

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be undertaking a range of activities on South Road, between Day Terrace and Torrens Road.

The works will be undertaken intermittently between 7pm and 6am from Tuesday 3 October to Monday 16 October 2017 (finishing 6am Monday 16 October).

Key activities

  • Excavation and wall trimming of the lowered motorway between Forster Street and Torrens Road.
  • Installation of directional road signs on South Road between Day Terrace and Torrens Road.
  • Investigation of stormwater infrastructure.

Excavators, loaders, vacuum truck, hand tools, trucks and light vehicles will be used to perform these works. Lighting towers will also be in operation during night works.

Traffic Management

No additional pedestrian or traffic management will be required to carry out the lowered motorway excavation works.

Lane and speed restrictions will apply on South Road in the vicinity of the sign installation works.

Works will be managed to minimise disturbance to local residents however some minor noise can be expected at times.

For further information about these works please contact us on: 1300 794 899, or email at: enquiries@t2talliance.com.au