UPCOMING WEEKEND WORKS WITH TEMPORARY ROAD CLOSURES: HYTHE STREET JUNCTION WITH SOUTH ROAD, AND MONMOUTH STREET JUNCTION WITH SOUTH ROAD, RIDLEYTON – 10/02/2017 – 12/02/2017

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be undertaking sewer works on South Road, between Hythe Street and Monmouth Street.

To safely facilitate these works, Hythe Street and Monmouth Street will be temporarily closed at South Road intermittently between 7pm Friday 10 February to 6am Sunday 12 February 2017.

Key activities

  • Saw cutting manhole.
  • Grouting sewer main.

A road saw, concrete truck and light vehicles will be used to perform these works. Lighting towers will also be in operation during night works.

Traffic Management

  • Signage will be in place to alert motorists to alternate access arrangements via Paget Street or Forster Street.
  • Pedestrian access will be maintained on South Road.
  • Access to properties will be maintained.
  • Lane and speed restrictions will apply on South Road in the vicinity of the works.

Works will be managed to minimise disturbance to local residents however some noise can be expected.