UPCOMING WEEKEND AND NIGHT WORKS ON SOUTH ROAD BETWEEN OVERLAND ROAD AND TAIT STREET, RENOWN PARK- 1 – 4 DECEMBER 2017

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be undertaking excavation and asphalting works in the southbound lanes of South Road from just south of Overland Road to Tait Street, Renown Park.

To minimise disturbance to peak hour traffic, and weather permitting, the works will be undertaken from 7pm Friday 1 December to 6am Monday 4 December 2017.

Key activities        

  • Movement of traffic barriers during night shift
  • Excavation of existing pavement, installation of gravel and asphalting during daylight hours.
  • Line marking.

Equipment

An excavator, mobile cranes, compaction equipment, a rock breaker, road saw, vacuum truck, asphalting equipment, line-marking equipment, trucks and light vehicles will be used to perform these works. Lighting towers will also be in operation during night works.

Some noise and vibration can be expected during these works, however, the work will be managed to minimise disturbance to local

residents and businesses as much as possible.

Traffic management

  • Tait Street will be partially closed to traffic during these works:

o   Access in to Tait Street from South Road will be maintained.

o   Traffic wanting to exit on to South Road will be redirected to Bishop Street or Torrens Road.

  • Lane and speed restrictions will apply in the vicinity of the works.
  • Signage will alert motorists and pedestrians to the changed traffic conditions.

For more information

For more information about these works, including the latest traffic arrangements, please visit: www.t2talliance.com.au email: enquiries@t2talliance.com.au  or call: 1300 794 899.

Please check the T2T Alliance website to confirm that these works are proceeding in case of wet weather.