UPCOMING WEEKEND AND NIGHT WORKS: WATER MAIN INSTALLATION – GRANGE ROAD, WEST HINDMARSH AND MANTON STREET, HINDMARSH – 26/02/2016 – 29/02/2016

The T2T Alliance is undertaking a range of activities to install a new water main along the northern side of Grange Road and Manton Street between Bertie Street, West Hindmarsh and Bacon Street, Hindmarsh.

To minimise disruption to peak hour traffic, the work will be undertaken from 7pm Friday 26 February, 2016 to 6am Monday, 29 February, 2016.

Key activities include:

  • Installation of concrete traffic barriers, saw cutting of asphalt, trench excavation, followed by installation of a new water main, back filling and compacting the trench and asphalt reinstatement.

A small crane, saw cutter, excavator, vacuum truck, compacting equipment, trucks and light vehicles will be used to perform these works. Lighting towers will also be in operation.

Traffic Management

  • Some temporary lane closures and speed restrictions will apply on Grange Road and Manton Street and the South Road intersection during these works.
  • Signage will alert motorists to the changed traffic conditions.

Bus Stop Changes

  • Bus Stop 12 on both sides of Grange Road will be temporarily CLOSED. Signage will be in place directing passengers to the next bus stop.

Parking

  • No parking on Grange Road and Manton Street between Bertie Street, West Hindmarsh and Bacon Street, Hindmarsh will be allowed.

Local Road Closures

  • Cator Street and Bertie Street, West Hindmarsh will be temporarily CLOSED at the Grange Road end

Some noise from these activities can be expected at times, however, works will be managed to minimise disturbance to the local community as much as possible.

For further information about these works, including the latest traffic arrangements, call: 1300 794 899 or email: enquiries@t2talliance.com.au.