UPCOMING TEMPORARY CLOSURE OF OVERLAND ROAD AND NIGHT WORKS ON SOUTH ROAD BETWEEN PYM STREET AND OVERLAND ROAD, CROYDON PARK – 10-21 DECEMBER 2017

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be continuing to install a common services trench in the southbound lanes of South Road between Pym Street and Overland Road, Croydon Park.

To minimise disturbance to peak hour traffic and weather permitting, the works will take place between 7pm and 6am:

  • From Sunday 10 December to Saturday 16 December (finishing 6am Saturday 16 December)
  • From Sunday 17 December to Thursday 21 December (finishing 6am Thursday 21 December)

Overland Road will be temporarily closed at South Road each night between 7pm and 5am from Monday 11 December to Wednesday 13 December (reopening 5am Wednesday 13 December).

Key activities                                                                                                 

  • Excavation of trench
  • Installation of Common Services Trench
  • Backfill and reinstatement of pavement

A vac truck, excavator, road saw, asphalting equipment, compaction equipment, trucks and light vehicles will be used to perform these works. Lighting towers will also be in operation during night works.

Traffic management

  • Lane and speed restrictions will apply in the vicinity of the works
  • Signage will alert motorists to the changed traffic conditions
  • Overland Road will be closed at South Road each night between 7pm and 5am from Monday 11 December to Wednesday 13 December (reopening 5am Thursday 14 December)
  • Motorists will be detoured via Pym Street during these time

Works will be managed to minimise disturbance to local residents however some noise can be expected.

For further information about these works please contact us on: 1300 794 899, or email at: enquiries@t2talliance.com.au