UPCOMING NIGHT WORKS: WATER MAIN AND SEWER MAIN WORKS AT THE SOUTH ROAD AND TORRENS ROAD INTERSECTION- 18/11/2016 – 28/11/2016

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be capping the water main and installing a new sewer main on the eastern side of South Road between Tait Street and Torrens Road and on the western side of Torrens Road between Ellen Street and South Road.

To minimise disturbance to peak hour traffic, the works will take place from 7pm Friday 18 November to 6am Monday 28 November 2016.

Key activities

  • Identification of services.
  • Saw cutting of the road pavement.
  • Excavation of a trench and pipe laying.
  • Backfill, reinstatement and asphalting.

A vacuum truck, road saw, excavator, backhoe, crane, compaction and asphalting equipment and light vehicles will be used to perform these works. Lighting towers will also be in operation during night works.

Traffic Management

  • Lane and speed restrictions will apply on South Road and Torrens Road in the vicinity of the works.
  • Signage will alert motorists to the changed traffic conditions.
  • Access to driveways will be maintained during these works.

Some noise disturbance can be expected at times while these works are completed, however the work will be managed to minimise disturbance to local residents as much as possible.

For further information about these works, including the latest traffic arrangements, please contact us on: 1300 794 899, or email at: enquiries@t2talliance.com.au