UPCOMING NIGHT WORKS AND TEMPORARY LOCAL ROAD CLOSURES OF FORSTER AND MONMOUTH STREETS AT SOUTH ROAD, RIDLEYTON – 26/9/2016 – 1/10/2016

As part of the Torrens Road to River Torrens Project, the T2T Alliance is continuing with the relocation of services and the installation of a new water main on the eastern side of South Road between McInnes Street and Hythe Street.

The installation of the water main will take place between 7pm and 6am, from Monday 26 September to Saturday 1 October 2016, weather permitting.

To facilitate these works:

  • Forster Street will be temporarily closed at South Road each night between 7pm and 6am, from Tuesday 27 September to Saturday 1 October 2016
  • Forster Street will be temporarily reopened to inbound traffic only at South Road each day between 6am and 7pm, from Wednesday 28 September to Friday 30 September 2016.
  • Monmouth Street will be temporarily closed at South Road each night between 7pm and 6am on Tuesday 4 October and Thursday 6 October 2016.

Key activities:

  • Saw cutting of the pavement, excavation of a trench and pipe laying.
  • Reinstatement and asphalting.

A vacuum truck, road saw, excavator, backhoe, bobcat, compaction equipment and light vehicles will be used to perform these works. Lighting towers will also be in operation during night works.

Traffic Management:

  • Traffic restrictions will apply at Forster Street and Monmouth Street at South Road as specified above.
  • Access to Forster Street and Monmouth Street will be available from Wood Avenue.
  • Traffic and speed restrictions on South Road will apply in the vicinity of the works.
  • Signage will be in place to alert motorists to the changed traffic conditions.

Works will be managed to minimise disturbance to local residents however some noise can be expected.

For further information about these works, including the latest traffic arrangements, please contact us on: 1300 794 899, or email at: enquiries@t2talliance.com.au