UPCOMING NIGHT WORKS ON SOUTH ROAD AT TAIT STREET, CROYDON PARK – 26 FEBRUARY – 1 MARCH 2018

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be installing stormwater infrastructure in the southbound lanes of South Road, at Tait Street, Croydon Park.

To minimise disturbance to peak hour traffic, night works will be undertaken each night between 7pm and 6am from Monday 26 February to Wednesday 28 February (finishing 6am Thursday 1 March), weather permitting.

Key activities

  • Excavation
  • Installation of stormwater pits and pipes
  • Backfill and reinstatement of pavement

An excavator, vacuum truck, road saw, mobile crane, compaction equipment, trucks and light vehicles will be used to perform these works. Lighting towers will also be in operation during night works.

Traffic management

  • Lane and speed restrictions will apply on South Road in the vicinity of the works.
  • Tait Street will continue to be closed during these works.
  • Signage will alert motorists to the changed traffic conditions.

 

For further information about these works please contact us on: 1300 794 899, or email at: enquiries@t2talliance.com.au