UPCOMING NIGHT WORKS ON SOUTH ROAD, RIDLEYTON – 1/8/2017 – 5/8/2017

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be continuing to install a new gas main between 191 South Road (Croydon Shopping Centre) and 225 South Road (SIGMA), Ridleyton.

To minimise disturbance to peak hour traffic, and weather permitting, the works will take place each night between 7pm and 6am from Tuesday 1 August to Saturday 5 August 2017 (finishing 6am Saturday 5 August).  

Key activities                                                                                               

  • Excavation to access gas pipes
  • Cutover of gas mains
  • Backfill and reinstatement of pavement

An excavator, road saw, backhoe, generator and light vehicles will be used to perform these works. Lighting towers will also be in operation during night works.

Traffic management

  • Access to driveways will be maintained during these works.
  • Lane and speed restrictions will apply in the vicinity of the works.
  • Signage will alert motorists to the changed traffic conditions.

Works will be managed to minimise disturbance to local residents however some noise can be expected.

For further information about these works, including the latest traffic arrangements, please visit www.t2talliance.com.au

You can also contact us on: 1300 794 899, or email at: enquiries@t2talliance.com.au