UPCOMING NIGHT WORKS ON SOUTH ROAD BETWEEN PYM STREET AND OVERLAND ROAD, CROYDON PARK- 25 FEBRUARY – 2 MARCH 2018

As part of the Torrens Road to River Torrens Project, the T2T Alliance is continuing a range of activities in the southbound lanes of South Road between Pym Street and Overland Road.

To minimise disturbance to peak hour traffic, night works will be undertaken each night between 7pm and 6am from Sunday 25 February to Friday 2 March (finishing 6am Saturday 3 March), weather permitting.

Key activities

  • Link in of new water main
  • Installation of Common Services Trench
  • Installation of street lighting

Excavators, vacuum trucks, mobile cranes, road saws, trucks and light vehicles will be used to perform these works. Lighting towers will also be in operation during night works.

Traffic management

  • Lane and speed restrictions will apply in the vicinity of the works.
  • Signage will alert motorists to the changed traffic conditions.

For further information about these works, including the latest traffic arrangements, please visit www.t2talliance.com.au