As part of the Torrens Road to River Torrens Project, the T2T Alliance will be installing gantries across South Road, between Port Road and the Outer Harbor rail bridge, Croydon. The gantries will be used to mount Intelligent Transport System infrastructure (electronic signage) which will be operational later in the year, when the lowered motorway is open.
To minimise disturbance to peak hour traffic, the works will be undertaken each night between 7pm and 6am on Wednesday 7 February and Thursday 8 February (finishing 6am Friday 9 February), weather permitting.
Key activities
Equipment
An elevated work platform, impact wrench, mobile cranes, trucks and light vehicles will be used to perform these works. Lighting towers will also be in operation during night works.
Some noise and vibration can be expected during these works, however, the work will be managed to minimise disturbance to local residents and businesses as much as possible.
Temporary traffic arrangements
From 10pm Thursday 8 February to 6am Friday 9 February 2018:
Pedestrians and cyclists
Cyclists should follow detour routes for motorists or dismount and use the available pedestrian access/crossings
For more information in these works, the latest traffic arrangements and detour routes, please visit: www.t2talliance.com.au email: enquiries@t2talliance.com.au or call: 1300 794 899. For real time traffic delay information, please visit: www.addinsight.com.au and download the app.
Please check the T2T Alliance website to confirm that these works are proceeding in case of adverse weather conditions.