UPCOMING NIGHT WORKS ON SOUTH ROAD BETWEEN PORT ROAD AND GAWLER AVENUE – 28/11/2016 – 2/12/2016 & 4/12/2016 – 9/12/2016

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be undertaking intermittent excavation works in the South Road median between Port Road and Gawler Avenue (north and south of the Grange Road bridge).

The works will be undertaken at the following times:

  • 7pm to 6am Monday 28 November to Friday 2 December 2016 (finishing 6am Friday 2 December 2016)
  • 7pm to 6am Sunday 4 December to Friday 9 December 2016 (finishing 6am Friday 9 December 2016).

Key Activities

  • Excavation works to install top of wall barriers
  • Excavation works to construct cantilevered fillets for Grange Road bridge

A vac truck, excavator, trucks, rock breaker (intermittent use only), light vehicles and lighting towers will be used to perform these works.

Traffic Management

  • There will be no disruptions to traffic on South Road as a result of these works.

Some noise disturbance can be expected at times while these works are completed, however the work will be managed to minimise disturbance to local residents as much as possible.

For further information about these works, including the latest traffic arrangements, please contact us on: 1300 794 899, or email at: enquiries@t2talliance.com.au