As part of the Torrens Road to River Torrens Project, the T2T Alliance will be continuing to install a new water main at the South Road intersection with Pym Street, Croydon Park.
To minimise disturbance to peak hour traffic, and weather permitting, these works will be undertaken each night between 7pm and 6am from Sunday 7 January to Tuesday 9 January (finishing 6am Wednesday 10 January).
Key activities
A road saw, excavator, trucks, compaction equipment and light vehicles will be used to perform these works. Lighting towers will also be in operation during night works.
Traffic management
Works will be managed to minimise disturbance to local residents however some noise can be expected.
For further information about these works please contact us on: 1300 794 899, or email at: enquiries@t2talliance.com.au