UPCOMING NIGHT WORKS AT THE SOUTH ROAD INTERSECTION WITH HAWKER STREET, RIDLEYTON – 13 – 17 NOVEMBER 2017

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be undertaking preparation works to install new kerbing at the South Road intersection with Hawker Street.

To minimise disturbance to peak hour traffic, and weather permitting, the works will be undertaken each night between 7pm and 6am from Monday 13 November to Friday 17 November 2017 (finishing 6am Saturday 18 November).

Key activities

  • Removal of existing kerb.
  • Excavation and preparation works for new kerbing.

Excavator, road saw, compaction equipment, trucks and light vehicles will be used to perform these works. Lighting towers will also be in operation during night works.

Traffic Management

  • Lane and speed restrictions will apply in the vicinity of the works.
  • Signage will alert motorists to the changed traffic conditions.

Works will be managed to minimise disturbance to local residents however some minor noise can be expected at times.

For further information about these works, including the latest traffic arrangements, please visit www.t2talliance.com.au

You can also contact us on: 1300 794 899, or email at: enquiries@t2talliance.com.au