UPCOMING NIGHT WORKS AT THE SOUTH ROAD INTERSECTION WITH HAWKER STREET INCLUDING TEMPORARY REMOVAL OF LEFT TURNS – 03/07/2017 FOR APPROXIMATELY ONE MONTH

As previous advised, as part of the Torrens Road to River Torrens Project, the T2T Alliance will be installing a new water main in the southbound lanes of South Road, across the intersection with Hawker Street this weekend from 7pm Friday 30 June to 6am Monday 3 July 2017, weather permitting.

Key activities

Saw cutting of the road pavement, excavation of trench and installation of water main.

Equipment

A road saw, excavator, mobile crane, welding and compaction equipment, trucks and light vehicles will be used to perform these works. Lighting towers will also be in operation during night works.

Traffic management

  • Lane and speed restrictions will apply in the vicinity of the works.
  • Signage will alert motorists to the changed traffic conditions.

From 1am Monday 3 July 2017, for approximately one month, left turns from Hawker Street onto South Road will not be permitted. Motorists will be required to turn right onto South Road from Hawker Street and use the Bedford Street u-turn facility to head south.

For further information about these works please Contact us on: 1300 794 899, or email at: enquiries@t2talliance.com.au