UPCOMING NIGHT WORKS AT THE SOUTH ROAD INTERSECTION WITH GRANGE ROAD/MANTON STREET- 11/5/2017 – 12/5/2017

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be undertaking preparation works to install kerbing and asphalt in the north west corner of the South Road intersection with Grange Road.

To minimise disturbance to peak hour traffic, the works will be undertaken intermittently between 7pm and 6am on Thursday 11 May and Friday 12 May 2017 (finishing 6am Saturday 13 May 2017), weather permitting.

Key activities

  • Cutting and removal of existing pavement
  • Levelling and

Equipment                                                                                                                  

A road saw, excavator, trucks and light vehicles will be used to perform these works. Lighting towers will also be in operation during night works.

Traffic management

  • Pedestrian access will be maintained.
  • Lane and speed restrictions will apply in the vicinity of the works.
  • Signage will alert motorists to the changed traffic conditions.

Some noise can be expected, however the work will be managed to minimise disturbance to local residents as much as possible.

For further information about these works, including the latest traffic arrangements, please visit www.t2talliance.com.au

You can also contact us on: 1300 794 899, or email at: enquiries@t2talliance.com.au