UPCOMING NIGHT WORKS ON SOUTH ROAD, HINDMARSH – 09/08/2017 – 18/08/2017

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be continuing to install a new water main in the southbound lanes of South Road, between Manton Street and Adam Street.

To minimise disturbance to peak hour traffic, and weather permitting, night works will be undertaken during the following times:

  • each night between 7pm and 6am on Wednesday 9 August and Thursday 10 August 2017 (finishing 6am Friday 11 August 2017).
  • between 7pm and 6am from Sunday 13 August to Friday 18 August 2017 (finishing 6am Friday 18 August 2017).

Key activities

  • Excavation of trench
  • Installation of pipe
  • Backfill and reinstatement of pavement

Excavators, vacuum trucks, road saws, trucks and light vehicles will be used to perform these works. Lighting towers will also be in operation during night works.

Traffic Management

  • Lane and speed restrictions will apply in the vicinity of the works.
  • Signage will alert motorists to the changed traffic conditions.

For further information about these works please contact us on: 1300 794 899, or email at: enquiries@t2talliance.com.au