UPCOMING NIGHT WORKS ON SOUTH ROAD, CROYDON PARK – 13-15 SEPTEMBER 2017

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be undertaking piling works on South Road near Overland Road, Croydon Park between 7pm and 6am from Wednesday 13 September to Friday 15 September 2017 (finishing 6am Friday 15 September).
Key activities

  • Installation of gantry footings

An excavator, piling rig, concrete truck and light vehicles will be used to perform these works. Lighting towers will also be in operation during night works.

Traffic management

  • Lane and speed restrictions will apply in the vicinity of the works.
  • Signage will alert motorists to the changed traffic conditions.

Noise disturbance and some vibration can be expected intermittently during these works. However, the work will be managed to minimise disturbance to local residents and businesses as much as possible.