UPCOMING NIGHT WORKS ON SOUTH ROAD BETWEEN ADAM STREET, HINDMARSH AND WEBER STREET THEBARTON- 11/4/2017 – 13/4/2017

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be undertaking road works in between Adam Street, Hindmarsh and Weber Street, Thebarton, in preparation for widening of Taylor Bridge

To minimise disturbance to peak hour traffic, the works will take place each night between 7pm and 6am on Tuesday 11 April and Wednesday 12 April 2017 (finishing 6am Thursday 13 April 2017).

Key activities                                                                                                          

  • Saw cutting of the road pavement.
  • Removal of centre median.
  • Reinstatement of pavement and asphalting.

A vacuum truck, road saw, rock breaker, excavator, bobcat, asphalt paver, compaction equipment, trucks and light vehicles will be used to perform these works. Lighting towers will also be in operation during night works.

Traffic management

  • Access to driveways will be maintained during these works.
  • Lane and speed restrictions will apply on South Road in the vicinity of the works.
  • Signage will alert motorists to the changed traffic conditions.

Some noise can be expected, however the work will be managed to minimise disturbance to local residents as much as possible.

For further information about these works, including the latest traffic arrangements, please visit www.t2talliance.com.au

You can also contact us on: 1300 794 899, or email at: enquiries@t2talliance.com.au