UPCOMING NIGHT WORKS: SEWER MAIN WORKS – SOUTH ROAD INTERSECTION WITH TORRENS ROAD – 14/10/2016 – 19/10/2016

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be continuing installation of a new sewer main on the eastern side of South Road at the Torrens Road intersection.

To minimise disturbance to peak hour traffic, the works will take place:

  • From 7pm Friday 14 October to 6am Monday 17 October 2016.
  • Between 7pm and 6am on Monday 17 October, Tuesday 18 October and Wednesday 19 October 2016 (finishing 6am Thursday 20 October 2016).

Key activities

  • Identification of services.
  • Saw cutting of the pavement.
  • Excavation of a trench and pipe laying.
  • Backfill, reinstatement and asphalting.

Traffic Management

  • Traffic and speed restrictions at the Torrens Road Intersection with South Road and on South Road between Tait Street and Dartmouth Street (for southbound traffic) will apply while works are in progress.
  • Signage will alert motorists to the changed traffic conditions.

Some noise disturbance can be expected at times while these works are completed, however the work will be managed to minimise disturbance to local residents as much as possible.