UPCOMING NIGHT WORKS: SEWER MAIN WORKS – 13/9/2016 – 20/9/2016

The T2T Alliance will be installing a new sewer on the eastern side of South Road at the Torrens Road intersection

To minimise disturbance to peak hour traffic, the works will take place between 7pm and 6am from Tuesday 13 September to Tuesday 20 September 2016 (finishing 6am Wednesday 21 September 2016).

Key activities

  • Identification of services.
  • Saw cutting of the pavement.
  • Excavation of a trench and pipe laying.
  • Backfill, reinstatement and asphalting.

A vacuum truck, road saw, excavator, backhoe, bobcat, compaction equipment and light vehicles will be used to perform these works. Lighting towers will also be in operation during night works.

Traffic Management

  • Traffic and speed restrictions at the Torrens Road Intersection with South Road and on South Road between Tait Street and Dartmouth Street (for southbound traffic) will apply while works are in progress.
  • Signage will alert motorists to the changed traffic conditions.

Some noise disturbance can be expected at times while these works are completed, however the work will be managed to minimise disturbance to local residents as much as possible.