UPCOMING NIGHT WORKS: SERVICE RELOCATION WORKS ON SOUTH ROAD BETWEEN TORRENS ROAD AND HAWKER STREET – 31/10/2016 – 05/11/2016

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be installing a new water main and stormwater main on the eastern side of South Road between Torrens Road and Hawker Street.

Crews will be working across various sites within the area to complete the works.

To minimise disturbance to peak hour traffic, the works will take place each night between 7pm and 6am from Monday 31 October to Saturday 5 November 2016 (finishing 6am Saturday 5 November 2016), weather permitting.

Key activities

  • Identification of services.
  • Saw cutting of the pavement.
  • Excavation of a trench and pipe laying.
  • Backfill, reinstatement and asphalting.

A vacuum truck, road saw, excavator, backhoe, bobcat, compaction equipment and light vehicles will be used to perform these works. Lighting towers will also be in operation during night works.

Traffic Management

  • Lane and speed restrictions on South Road will apply in the vicinity of the works.
  • Signage will alert motorists to the changed traffic conditions.
  • Pedestrian access on South Road will be maintained with the assistance of a traffic controller.

Some noise disturbance can be expected at times while these works are completed, however the work will be managed to minimise disturbance to local residents as much as possible.

For further information about these works please contact us on: 1300 794 899, or email at: enquiries@t2talliance.com.au