UPCOMING NIGHT WORKS: SERVICE RELOCATION WORKS ON SOUTH ROAD BETWEEN HAWKER STREET AND FORSTER STREET – 31/07/2016 TO 04/08/2016

 

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be continuing construction of a Common Services Trench within the eastern footpath of South Road, between the Hawker Street intersection and Forster Street.

To minimise disturbance to peak hour traffic, the works will take place each night between 7pm and 6am from Sunday 31 July to Thursday 4 August 2016 (finishing 6am Friday 5 August 2016), subject to weather conditions.

Key activities

  • Removal of the footpath along the eastern side of South Road.
  • Excavation or directional drilling of the Common Services Trench (location dependent).
  • Reinstatement of the footpath and property driveways with a temporary finish.

A vacuum truck, rock breaker, road saw, mobile crane, excavator, drill rig, compaction equipment, trucks and light vehicles will be used to perform these works. Lighting towers will also be in operation during night works.

We will contact property occupiers should access to the property be impacted during the works.

Traffic Management

  • Traffic and speed restrictions on South Road and at the South Road and Hawker Street intersection will apply.
  • Traffic movements will continue to be provided as normal at the South Road and Hawker Street intersection.
  • Traffic and speed restrictions on South Road will apply in the vicinity of the works.
  • Signage will alert motorists to the changed traffic conditions.
  • Pedestrian access on South Road will be maintained with the assistance of a traffic controller.

Some noise disturbance can be expected at times while these works are completed, however the work will be managed to minimise disturbance to local residents as much as possible.

For further information about these works please contact us on: 1300 794 899, or email: enquiries@t2talliance.com.au.