UPCOMING NIGHT WORKS: SERVICE RELOCATION WORKS- 13/9/2016 – 20/9/2016

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be directional drilling communication conduits across the eastern side of Torrens Road at the South Road intersection.

To minimise disturbance to peak hour traffic, the works will take place between 7pm and 6am from Tuesday 13 September to Tuesday 20 September 2016 (finishing 6am Wednesday 21 September 2016). No directional drilling works will be undertaken on Saturday 17 September or Sunday 18 September 2016.

Key activities

  • Excavation of entry and exit pit.
  • Directional drilling across Torrens Road at the South Road intersection from the northeast corner to the southeast corner of the intersection.
  • Backfill and reinstatement of pits.

A vacuum truck, drill rig, excavator, bobcat, trucks and light vehicles will be used to perform these works. Lighting towers will also be in operation during night works.  Equipment to facilitate these works will be set up on the northeast and southeast corner of the South Road intersection with Torrens Road.

Traffic Management

  • Traffic restrictions and speed restrictions on South Road will apply while works are in progress.
  • Signage will alert motorists to the changed traffic conditions.

Some noise disturbance can be expected at times while these works are completed, however the work will be managed to minimise disturbance to local residents as much as possible.

For further information about these works, including the latest traffic arrangements, please contact us on: 1300 794 899, or email at: enquiries@t2talliance.com.au