UPCOMING NIGHT WORKS ON PORT ROAD – 29/8/2016 – 2/9/2016

The T2T Alliance will be installing a new water main in the city bound lanes of Port Road between Bertie Street and South Road.

To minimise disturbance to peak hour traffic, the works will take place between 7pm and 6am from Monday 29 August to Friday 2 September 2016 (finishing 6am Saturday 3 September 2016).

Key activities

  • Service depthing to confirm the location of services.
  • Excavation of trench.
  • Installation of water main.
  • Reinstatement of trench.

Traffic Management

  • Speed and traffic restrictions on Port Road will apply in the vicinity of the works.
  • Signage will alert motorists to the changed traffic conditions.

Some noise can be expected while these works are completed, however the work will be managed to minimise disturbance to local residents as much as possible.

For further information about these works, including the latest traffic arrangements, please contact us on: 1300 794 899, or email: enquiries@t2talliance.com.au