UPCOMING NIGHT WORKS ON TORRENS ROAD NEAR DAYS ROAD, RENOWN PARK / WEST CROYDON – 18 – 19 JULY 2018

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be undertaking signalling works in the centre median of Torrens Road, just east of the intersection with Days Road.

To minimise disturbance to peak hour traffic, and weather permitting, these works will be undertaken intermittently each night between 7pm and 6am on Wednesday 18 July and Thursday 19 July (finishing 6am Friday 20 July).

Key activities                                                                                               

  • Excavation and installation of signalling conduit.
  • Backfill and reinstatement.

A road saw, vacuum truck, hand tools, compaction equipment and light vehicles will be used to perform these works. Lighting towers will also be in operation during night works.

Traffic management

  • Lane and speed restrictions will apply on Torrens Road in the vicinity of the works.
  • Signage will alert motorists to the changed traffic conditions.

Works will be managed to minimise disturbance to local residents however some noise can be expected.