UPDATE: UPCOMING NIGHT WORKS ON SOUTH ROAD OPPOSITE DARTMOUTH STREET – 18-19 MAY 2018

Due to scheduling conflicts, these works will now be undertaken from 7pm Friday 18 May to 6am Saturday 19 May.

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be continuing to install new stormwater infrastructure in the southbound lanes of South Road opposite Dartmouth Street.

To minimise disturbance to peak hour traffic, and weather permitting, these works will be undertaken from 7pm Friday 18 May to 6am Saturday 19 May.

Key activities                                                                                               

  • Excavation and installation of stormwater pits and pipes.
  • Backfill and reinstatement of pavement.

A road saw, vacuum truck, excavator, backhoe, trucks, compaction equipment and light vehicles will be used to perform these works. Lighting towers will also be in operation during night works.

Traffic management

  • Lane and speed restrictions will apply in the vicinity of the works.
  • Signage will alert motorists to the changed traffic conditions.

Works will be managed to minimise disturbance to local residents however some noise can be expected.

For further information about these works please contact us on: 1300 794 899, or email at: enquiries@t2talliance.com.au