UPCOMING NIGHT WORKS ON SOUTH ROAD BETWEEN OVERLAND ROAD AND TORRENS ROAD – 26 – 29 MARCH & 2 – 8 APRIL 2018

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be continuing a range of activities in the southbound lanes of South Road between Overland Road and Torrens Road.

To minimise disturbance to peak hour traffic, and weather permitting, these works will be undertaken intermittently each night between 7pm and 6am during the following times:

  • From Sunday 25 March to Wednesday 29 March (finishing 6am Thursday 30 March).
  • From Monday 2 April to Sunday 8 April (finishing 6am Monday 9 April).

Key activities                                                                                               

  • Installation of electrical connections.
  • Backfill and reinstatement of footpath, kerbing and driveways.
  • Pavement works.

A vacuum truck, excavator, trucks, and light vehicles will be used to perform these works. Lighting towers will also be in operation during night works.

Traffic management

  • Signage will be in place to direct pedestrians and motorists.
  • Speed restrictions will apply in the vicinity of the works.

Works will be managed to minimise disturbance to local residents however some noise can be expected.

For further information about these works, including the latest traffic arrangements, please visit www.t2talliance.com.au

You can also contact us on: 1300 794 899, or email at: enquiries@t2talliance.com.au