UPCOMING NIGHT WORKS ON SOUTH ROAD BETWEEN ADAM STREET, HINDMARSH AND PYM STREET, CROYDON PARK – FROM MONDAY 12 NOVEMBER FOR APPROXIMATELY THREE WEEKS

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be undertaking a range of finishing works in various locations along South Road between Adam Street and Pym Street.

To minimise disturbance to peak hour traffic, and weather permitting, these works will be undertaken intermittently each night between 7pm and 6am from Monday 12 November for approximately three weeks.

Key activities                                                                                               

  • Rectification of service utility pits.
  • Painting of bike lanes.

A road saw, vacuum truck, excavator, trucks, hand tools and light vehicles will be used to perform these works. Lighting towers will also be in operation during night works.

Traffic management

  • Lane and speed restrictions will apply in the vicinity of the works.
  • Signage will alert motorists to the changed traffic conditions.

Works will be managed to minimise disturbance to local residents however some minor noise can be expected.

For further information about these works, including the latest traffic arrangements, please visit www.t2talliance.com.au

You can also contact us on: 1300 794 899, or email at: enquiries@t2talliance.com.au