UPCOMING NIGHT WORKS INCLUDING TEMPORARY CLOSURE OF DAY TERRACE JUNCTION WITH ELIZABETH STREET, CROYDON- 3 – 7 DECEMBER 2017

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be continuing to install new kerbing and footpaths at the Queen Street level crossing, and along Elizabeth Street to Day Terrace (western side).

To minimise disturbance to traffic, and weather permitting, the works will be undertaken intermittently from 7pm Sunday 3 December and 6am Thursday 7 December 2017.

Key activities

  • Removal of existing kerb.
  • Excavation, preparation and pouring for new kerbing and footpath.

Excavator, road saw, compaction equipment, trucks and light vehicles will be used to perform these works. Lighting towers will also be in operation during night works.

Traffic Management

  • The Elizabeth Street junction with Day Terrace (western side) will be temporarily closed during these works.
  • Access to Day Terrace, between Elizabeth Street and Thomas Street, will be available via Thomas Street.
  • Signage will alert motorists to the changed traffic conditions.

As previously advised, the Queen Street level crossing will also be closed during these times. Works will be managed to minimise disturbance to local residents however some minor noise can be expected at times.

For further information about these works, including the latest traffic arrangements, please visit www.t2talliance.com.au

You can also contact us on: 1300 794 899, or email at: enquiries@t2talliance.com.au