UPCOMING NIGHT WORKS IN THE RAIL CORRIDOR AT THE QUEEN STREET LEVEL CROSSING – 13-14 APRIL 2018

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be repairing the pedestrian maze on the eastern side of the Queen Street level crossing.

To minimise disturbance to commuters, and weather permitting, these works will be undertaken from 11.30pm Friday 13 April to 6am Saturday 14 April.

Key activities                                                                                               

  • Asphalting of the pedestrian maze.

A profiler, compaction equipment and paver will be used to perform these works. Lighting towers will also be in operation during night works.

Traffic management

  • Pedestrian access across the rail corridor will be maintained.
  • Lane and speed restrictions will apply in the vicinity of the works.
  • Signage will alert motorists to the changed traffic conditions.

 

Works will be managed to minimise disturbance to local residents however some noise can be expected.

For further information about these works please contact us on: 1300 794 899, or email at: enquiries@t2talliance.com.au