UPCOMING NIGHT WORKS ON DAYS ROAD BETWEEN TORRENS ROAD AND LIBERTON AVENUE, CROYDON PARK- 9 – 12 January 2017

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be undertaking sewer main construction works on Days Road between Torrens Road and Liberton Avenue.

These works will be undertaken between 7pm and 6am from Monday 9 January to Thursday 12 January 2017 (finishing 6am Thursday 12 January).

Key activities            

  • Welding of manhole.
  • Air testing and commissioning.

A vacuum truck, excavator, trucks, welding equipment and light vehicles will be used to perform these works. Lighting towers will also be in operation during night works.

Traffic Management

  • Lane and speed restrictions will apply on Days Road, Lamont Street, Torrens Road and Liberton Avenue at various times, in the vicinity of the works.
  • Signage will alert motorists to the changed traffic conditions.
  • Access to properties will be maintained.

Works will be managed to minimise disturbance to local residents however some noise can be expected.

For further information about these works, including the latest traffic arrangements, please contact us on: 1300 794 899, or email at: enquiries@t2talliance.com.au