UPCOMING NIGHT WORKS ON THE CORNER OF SOUTH ROAD AND TAIT STREET, CROYDON PARK- 22 – 23 FEBRUARY 2018

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be installing a stormwater pit on the northern corner of South Road and Tait Street, Croydon Park.

To minimise disturbance to peak hour traffic, night works will be undertaken from 7pm Thursday 22 February to 6am Friday 23 February, weather permitting.

Key activities

  • Excavation
  • Installation of stormwater pit
  • Backfill and reinstatement of pavement

An excavator, vacuum truck, road saw, mobile crane, trucks and light vehicles will be used to perform these works. Lighting towers will also be in operation during night works.

Traffic management

  • Lane and speed restrictions will apply in the vicinity of the works.
  • Signage will alert motorists to the changed traffic conditions.

For further information about these works, including the latest traffic arrangements, please visit www.t2talliance.com.au

You can also contact us on: 1300 794 899, or email at: enquiries@t2talliance.com.au