UPCOMING NIGHT WORKS AT THE CEDAR AVENUE AND TORRENS ROAD INTERSECTIONS WITH SOUTH ROAD – 3-10 NOVEMBER 2017

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be installing inclinometers on South Road near the intersection with Cedar Avenue and near the intersection with Torrens Road.

To minimise disturbance to peak hour traffic, and weather permitting, the works will be carried out each night between 7pm and 6am from:

  • Friday 3 November 2017 (finishing 6am Saturday 4 November 2017).
  • Monday 6 November to Thursday 9 November 2017 (finishing 6am Friday 10 November 2017).

Key activities                                                                                                 

  • Saw cutting of the pavement and boring.
  • Installation of inclinometer.
  • Backfill and reinstatement of pavement.

A vacuum truck, road saw, drill rig, concrete mixer, trucks and light vehicles will be used to perform these works. Lighting towers will also be in operation during night works.

Traffic management

  • Lane and speed restrictions will apply in the vicinity of the works.
  • Signage will alert motorists to the changed traffic conditions.

Works will be managed to minimise disturbance to local residents however some noise can be expected.

For further information about these works please contact us on: 1300 794 899, or email at: enquiries@t2talliance.com.au