UPCOMING NIGHT WORKS: ASPHALTING WORKS ON SOUTH ROAD – 3/4/2017 – 4/4/2017

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be reinstating asphalt in the southbound lanes of South Road between Manton Street and Gawler Avenue.

To minimise disturbance to peak hour traffic, the works will take place between 7pm and 6am on Monday 3 April and Tuesday 4 April 2017 (finishing 6am Wednesday 5 April 2017).    

A vacuum truck, excavator, asphalt paver, roller, trucks and light vehicles will be used to perform these works.

Traffic Management

  • Lane and speed restrictions will apply in the vicinity of the works.
  • Signage will alert motorists to the changed traffic conditions.

Some noise disturbance can be expected at times while these works are completed, however the work will be managed to minimise disturbance to local residents as much as possible.

For further information about these works, including the latest traffic arrangements, please visit www.t2talliance.com.au

You can also contact us on: 1300 794 899, or email at: enquiries@t2talliance.com.au