As part of the Torrens Road to River Torrens Project, the T2T Alliance will be undertaking a range of day and night works in the southbound lanes of South Road, between Pym Street and Tait Street, from October 2017 to early 2018. Further details will be provided as the works progress.
The works will include:
To safely undertake this program of works, southbound traffic on South Road will be temporarily switched to new lanes between Pym Street and just north of the Tait Street u-turn facility from Monday 9 October 2017 until early 2018.
To minimise disruption to traffic, the traffic switch will take place between 5pm Sunday 8 October and 6am Monday 9 October 2017.
Key activities
Mobile cranes, line-marking equipment, trucks and light vehicles will be used to perform these works. Lighting towers will be in operation during night works.
Some noise can be expected, however the work will be managed to minimise disturbance to local residents and businesses as much as possible.
Access to properties on South Road from 6am Monday 9 October to early 2018
Sunbeam Road
From 6am Monday 9 October 2017 access to Sunbeam Road will be provided via a one way service road. Entry to the one way service road will be from Overland Road, near the junction with South Road. To access South Road from Sunbeam Road, motorists will need to turn left on to the one way service road and merge on to South Road, just north of the Tait Street u-turn facility.
Pedestrians
Pedestrian access will continue to be provided, unless notified otherwise.
Overland Road Shops
Access to the Overland Road shops will continue to be provided via South Road or Overland Road. Additional parking will also be provided on South Road.
For more information, please call 1300 794 899, or email: enquiries@t2talliance.com.au. Please also visit: www.addinsight.com.au and download the app.