As part of the Torrens Road to River Torrens Project, the T2T Alliance will be undertaking pavement works on South Road between Royce Avenue and Overland Road (finishing approximately 100 meters north of Overland Road).
To minimise disturbance to peak hour traffic, the works will be undertaken from 7pm Friday 9 March to 6am Tuesday 13 March, weather permitting. Testing of the pavement will also be undertaken intermittently from 7pm Tuesday 13 March to 6am Wednesday 14 March.
Key activities
An excavator, profiler, compaction equipment, asphalt paver, rock breaker (intermittent only), trucks and light vehicles will be used to perform these works. Lighting towers will also be in operation during night works.
Traffic management
For further information about these works please contact us on: 1300 794 899, or email at: enquiries@t2talliance.com.au