UPDATE: NIGHT WORKS ON SOUTH ROAD BETWEEN PYM STREET AND SUNBEAM ROAD, CROYDON PARK – 05/06/2017 – 09/06/2017

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be undertaking asphalting, line-marking and associated works in the median area on South Road, between Pym Street and Sunbeam Road.

Due to weather conditions, some works could not be completed in the previously advised time.

Works will be undertaken intermittently between 7pm and 6am from Monday 5 June to Friday 9 June 2017 (finishing 6am Friday 9 June 2017)

Key activities

  • Installation of traffic barriers, asphalt and line-marking
  • Removal of kerbing
  • Service identification

A grader, profiler, compaction equipment, asphalt paver, line-marking equipment, compaction equipment, trucks and light vehicles will be used to perform these works. Lighting towers will also be in operation during night works.

Some noise disturbance can be expected, however the work will be managed to minimise disturbance to local residents as much as possible.

During these works, lane and speed restrictions will apply on South Road in the vicinity of the works.

The previously advised temporary changes to traffic arrangements have been postponed. New timings will be communicated closer to these changes coming into effect.

Thank you for your ongoing patience while these important works are being undertaken.

For further information about these works, including the latest traffic arrangements, please visit www.t2talliance.com.au. You can also contact us on: 1300 794 899, or email at: enquiries@t2talliance.com.au