UPCOMING NIGHT AND WEEKEND WORKS AT THE SOUTH ROAD INTERSECTION WITH TORRENS ROAD- 6 – 15 SEPTEMBER 2017

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be continuing to undertake a range of activities at the South Road intersection with Torrens Road.

To minimise disturbance to peak hour traffic, and weather permitting, the works will be carried out during the following times:

  • between 7pm and 6am on Wednesday 6 September and Thursday 7 September 2017
  • from 7pm Friday 8 September to 6am Monday 11 September 2017
  • each night between 7pm and 6am from Monday 11 September to Friday 15 September 2017 (finishing 6am Friday 15 September 2017)

Key activities                                                                                               

  • Installation of signalling conduits
  • Installation of stormwater infrastructure
  • Bridge works
  • Excavation of the lowered motorway and wall trimming

A vacuum truck, road saw, excavator, compaction equipment, trucks and light vehicles will be used to perform these works. Lighting towers will also be in operation during night works.

Traffic management

  • Lane and speed restrictions will apply in the vicinity of the works.
  • Signage will alert motorists to the changed traffic conditions.

Works will be managed to minimise disturbance to local residents however some noise can be expected.

For further information about these works, including the latest traffic arrangements, please visit www.t2talliance.com.au

You can also contact us on: 1300 794 899, or email at: enquiries@t2talliance.com.au