UPCOMING NIGHT AND WEEKEND WORKS ON SOUTH ROAD BETWEEN DARTMOUTH STREET AND HAWKER STREET, RIDLEYTON – 30/06/2017 – 03/07/2017

As part of the Torrens Road to River Torrens Project, the T2T Alliance is undertaking pavement and asphalt reinstatement works in the southbound lanes on South Road between Dartmouth Street and Hawker Street.

To minimise disruption to peak hour traffic, these works will be undertaken from 7pm Friday 30 June to 6am Monday 3 July 2017. Access to some driveways may be temporarily impacted during these works. Residents and business operators will be notified in advance of any works that will have a direct impact, such as temporary driveway restrictions.

Key activities

  • Removal of existing road pavement
  • Laying new pavement, asphalting and line-marking

An excavator, profiler, compaction equipment, asphalt paver, line-marking equipment, hand tools, trucks and light vehicles will be used to perform these works. Lighting towers will also be in operation during night works.

Some noise and vibration can be expected, however the works will be managed to minimise disturbance to local residents and businesses as much as possible.

Temporary traffic arrangements

From 7pm Friday 30 June to 6am Monday 3 July 2017:

  • One lane will be maintained on South Road southbound between Dartmouth Street and Hawker Street.
  • The u-turn facility at Bedford Street for northbound traffic on South Road will be temporarily closed. Motorists can use the u-turn facility at Tait Street.
  • Signage will be in place to alert motorists to changes in traffic arrangements.
  • Pedestrian access will continue to be provided on South Road.
  • Traffic delays on South Road can be expected.

For further information about these works please contact us on: 1300 794 899, or email at: enquiries@t2talliance.com.au