UPCOMING NIGHT AND WEEKEND WORKS: SERVICE RELOCATION WORKS – PORT ROAD – 21/10/2016 – 24/10/2016

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be installing a new water main in the west bound lanes of Port Road, adjacent Hope Inn.

To minimise disturbance to peak hour traffic, the works will take place from 7pm Friday 21 October to 6am Monday 24 October 2016.

Key Activities and Equipment

  • Installation of a new water main.
  • Removal of existing valves.

A vacuum truck, road saw, excavator and light vehicles will be used to perform these works. Lighting towers will also be in operation during night works.

Traffic Management

  • Lane and speed restrictions will apply in the vicinity of the works.
  • Signage will alert motorists to the changed traffic conditions.
  • Pedestrian access will be maintained with traffic controller assistance.

Some noise disturbance can be expected at times while these works are completed, however the work will be managed to minimise disturbance to local residents as much as possible.

For further information about these works please contact us on: 1300 794 899, or email at: enquiries@t2talliance.com.au